K6 Output 28 V / OPEN: is reference ground required?

K6 Output 28 V / OPEN: is reference ground required?

When the K6 is configured as an OUTPUT providing 28 V or OPEN, and the K6 bank only requires VCC,is the reference ground required?

Normally yes, but please note that Built-in-Test (BIT) requires GND return to function